Platform X
Testing continues on Platform X (PX), our new platform for the submission, validation and reporting of CMP data.
We are currently still conducting parallel processing with the units who have volunteered to be involved in this testing phase. This has been a tremendously useful process, and we would again like to give our thanks to these units for their contributions.
As part of this parallel process testing for PX:
- 41 units have logged into the system
- 34 units have uploaded data
- 33 units have begun using the online DVRs
- 16 have at least one quarter of clean data
- 8 have uploaded a second quarter
- 5 have at least two quarters clean
We are now moving towards the end of this testing phase – our plan is for the Q2 July-September 2019 data submission to be the final parallel processing period. Once we reach this milestone, we will then be able to invite more units to transition to PX.
Finally, we would also like to thank all other units that have expressed an interest in onboarding to and testing PX. We will be keeping all units informed of progress.